Your DSO sets the local limits
Wholesale and balancing markets work the same way at every site in Germany, so differences come from the local grid. Your DSO sets the terms of your grid connection, and some DSOs attach additional restrictions, for example no discharging during midday hours. Local restrictions limit how freely your battery can follow market prices. With Entrix LocalFlex, we adapt the optimization to them.
Restrictions differ in what they cost
Depending on its type and level, a local restriction can barely matter or cost a large share of your battery’s revenue. Limits on charging power and caps on balancing services usually weigh most.
We calculate what your site costs before you build
Grid connection terms are usually fixed before a battery is built. Before you build, we calculate what the local restrictions cost your business case. You can compare sites and prepare the discussion with your DSO on those numbers. Once your battery trades, we build the restrictions into its optimization.